Work is being done to evaluate the anchorage strength
of hooked bars fabricated using two different epoxy-coating application
processes. Results will show whether the current ACI 318 provisions
are adequate for ensuring development length of epoxy coated hooked
bars independent of the coating application method. If predictable
bond behavior can be demonstrated, including strength and failure
mode, current ACI 318 provisions can be reaffirmed. If not, recommendations
will be suggested to reflect the findings.
Several exploratory batches of concrete have been made using locally
available glacial gravel and sand. Mix designs have been found which
produce average results at the target strengths. Batches have also
been made in order to produce a self consolidating concrete for
use in this research. More information on this project can be obtained
by contacting Paul Koning using the contact
form. |